PROJECT DETAILS
Dykon shot 75,586 feet of ditch and 30,161 cubic yards of rock on this 36-inch pipeline job. The West Virginia mountains provided ample difficult terrain for the crews. Winching is a must on steep hills and calls for a well-coordinated plan with the contractor and an organized shot loading process. The mountain bluffs presented their own unique challenges, especially when near a road or structure. Dykon successfully completed this job on schedule and with zero incidents.