Lowell, AR | 2003

Beaver Water District’s Beaver Lake Intake Facilities Expansion has
won a National “Award of Merit” in the Public Works/Environmental
Category from the Associated Builders and Contractors, as a part of its
annual Excellence In Construction Awards Program.

ABC National Award of Merit

PROJECT DETAILS

Northwest Arkansas, home of the Wal-Mart corporate offices, is one of the fastest growing residential and commercial hubs of the central United States.  The rapid growth of this area challenges civil engineers to meet the growing demand for power and water.

Beaver Water District treats and supplies a major portion of the drinking water for Bentonville and surrounding communities.  The current facility has a capacity of 70 million gallons of water per day, with a demand that is growing by leaps and bounds.  In response to this increasing demand for water, Beaver Water District has engineered and implemented an expansion project which will double the capacity of the existing treatment plant, with a built in capacity of an additional 60 million gallons per day if required in the future.

A team of engineers, geologists, and general construction workers took on this substantial project.  Their objective was to take a piece of lake-front property and turn it into a water pumping facility. The Beaver Water District’s intake facilities expansion started in May, 2003 and is due for completion in March, 2005, coinciding with the completion of Beaver Water District’s complete system upgrade.  The intake facilities expansion is a $13.4 Million project consisting of two new structures; the raw water intake structure with its support electrical building and the renovation of an existing prechlorination building.

Garney Companies, Inc. is the General Contractor for the Beaver Water District, Intake Facilities Expansion project.  The project is designed and managed by MWH Americas, Inc., in association with Bennett/Staheli Engineers, Sacramento, CA and McGoodwin, Williams & Yates, Inc., Fayetteville, AR.  Jim Holt, Garney’s Senior Project Manager, and Sandra Holt have temporarily relocated to Lowell, AR while this project is in progress.  With Jim’s ability to efficiently delegate work and his local labor, he has the project well underway.

To access the new water treatment plant site, it was necessary to clear and remove trees for the construction of two roads off of the existing water treatment road.  The site then required a substantial amount of earthwork to remove all dirt and material down to the bedrock.  The objective was to clear an area large enough to work and keep the slopes from sliding into the shafts, while minimizing the amount of disturbed land.  The twin shafts will contain the pumps that will feed water from the lake to the treatment plant through a 60” line.

Dykon Blasting Corp., Tulsa, OK, drilled and blasted these shafts through solid limestone and shale.   The 33-foot diameter shafts were blasted alternating from one to the other, achieving 10-foot deep cuts each time.  The outer walls of the shafts were drilled and trim blasted to protect the walls of the shaft from over break and produced picture-perfect, smooth walls in the limestone.

To meet the strict time line for this project, Garney’s skilled workforce used a crane for continuous movement of men, equipment, and materials back and forth between the two shafts.  The shafts were excavated alternating from one to the other to maximize production and minimize the potential for damage to the other shaft.

In order to meet the rigid time table, Garney, with the use of their crane, assisted the excavation in one shaft while Dykon’s workforce drilled and prepared the blasting for the other.

Garney Water Facilities Group has been in construction of the new intake facility for Beaver Water District since May of 2003. We have constructed a dual shaft intake structure that involved two 30 food diameter shafts approximately 90-feet deep.

Dykon Blasting Corp. was our blasting subcontractor for this project. As the project progressed we were very pleased with Dykon’s performance and would mention these things. At our project Dykon consistently proved they were a safety oriented company. They followed safety procedure to the letter. They proved also, they would do all they could to insure that Garney as general contractor met the schedule established for their work. Their people are knowledgeable and will take the time to explain in laymans terms what they are going to do, how they are going to do it, and what you can expect to happen.

We were pleased with Dykon’s performance, safety program, and attitude toward our goals as general contractor.

Jim Holt, General Superintendent, Garney Construction

Following the excavation, Underground Services Corp., Kansas City, MO shored the walls, installed rock bolts, chain link fence, and sprayed pumpable concrete on the walls.  Their work, although only a temporary fix, was a vital safety feature.  Shoring the walls kept rocks from falling off the walls as men worked in the bottom, excavating and blasting the shafts.  Working in these extremely confined and wet conditions required two shifts, seven days a week to achieve the desired production rate.

The concrete-lined shafts are 30-foot in diameter, 95-feet deep, and will contain eight 60-inch diameter lake-tap micro-tunnels.  The micro-tunnels will supply raw water to the shafts and range in length from 80-feet to 180-feet depending upon the depth.  By having different depths, different levels of water will be able to be selected to fill the shafts. This will result in selecting the best water quality at any given time.  There is also one 60-inch diameter, 60-foot long micro-tunnel used to connect the two shafts.

The lake-tap micro-tunnels reach out into the lake at various elevations.   Square, stepped benches were prepared in the rocky lakeshore to give the micro-tunnels uninterrupted access to the lake water.  Dykon Blasting Corp. expertise with underwater blasting was crucial for preparation of the stepped benches.   The hard limestone and varying geological layers of the lakeshore added degrees of difficulty to the underwater drilling and blasting.  The drilling was performed from a barge floating just off the lakeshore. The holes had to be loaded through PVC pipes acting as casings for the holes.  The step benches were precisely cut into the side of Beaver Lake and excavated with a clam bucket and long reach excavator.

Garney Companies, Inc. along with Dykon Blasting Corp., and Underground Services have paved the way for the construction of the new water treatment plant.  With the shafts completely excavated and the substructure underway, Beaver Water District will have a new raw water treatment plant in its near future.

We at Dykon Blasting would like to take this opportunity to express our gratitude to Garney Construction, MWH and the Beaver Water District for allowing us this unique opportunity to serve the area in this manner.  We have made new friends and we hope to see them again in the future.