Oklahoma | 2013

Dykon blasted 77,288 lineal feet [14.63 miles] of trench along with 81,617 cubic yards of mass rock.

Dykon Blasting

PROJECT DETAILS

The Seaway Pipeline was a joint venture between Enterprise Products and Enbridge Inc.  On this project Dykon was asked to perform all of the drilling and blasting for the contractor.  In total, Dykon shot over 76,000 feet of trench and over 81,000 cubic yards of mass rock.

77288
Ft of Trench Blasted
81617
Cu Yards of Rock Excavated