37 Shots in 6 weeks for a total of 626,090 Cubic Yards of Rock

Dykon Blasting

PROJECT DETAILS

Located in Waco, Texas, a new industrial park covering 40+ acres is currently under construction. This project required 30.9 acres of area be blasted on an aggressive time schedule. Dykon mobilized a fleet of high production drills and bulk loading equipment to get the job done on schedule. The entire 30.9 acres of rock area was safely drilled and shot to completion grade in six weeks.

426,820
Pounds of Explosives Used
1,344,716
Square Feet of Rock