PROJECT DETAILS
Dykon shot 31,307 feet of ditch in on these 30 miles of 12-inch pipeline. The contractor encountered rock that caused production to come to a standstill. Dykon was able to quickly mobilize and complete all blasting in 18 days, keeping the contractor on schedule and getting a big “thank you” for our ability to respond so quickly after receiving the call.