Bentonville, AR | 2009

We shot 884 feet of trench and used 7,138 pounds of explosives.

Dykon Blasting

PROJECT DETAILS

Dykon performed the mass rock and utility blasting for the City of Bentonville, in Arkansas.  The project, the 8th Street Extension, comprised of both utility blasting for water and sewer lines along with mass rock for new road placement.  Once again, the blasting had to be precise and calculated beforehand, as there were various homes parallel to the project.

884
Ft of Utility Trench Blasted
7138
Lbs of Explosive Used